Kuvaninga Energia – Chokwe; Mozambique
ADC was approached by an international developer to assist in a solution to effectively and efficiently utilise 3 million gigajoules of Mozambican Royalty Gas.
ADC conducted a Technology Due Diligence and selected 10 x GE Jenbacher 24 cylinder engines with a generation capacity of 40MW. ADC developed the project, at risk, over a period of 4 years to reach financial close in 2013. Construction of this gas facility commenced in June 2014 with ADC in the role of Owner’s Project Manager. The facility reached Deemed Commercial operation in December 2015.
ADC is appointed as the Kuvaninga facility’s Operations and Maintenance contractor for a period of 14 years.